Contractor estimate comparison worksheet

Copy these fields into a sheet, normalize the scope and send one clear clarification request to each bidder.

Set up the comparison before entering prices

Hands measuring a wooden plank
Photograph by Ono Kosuki

Use one column per proposal and keep its date or revision at the top. Write the outcome you want in one sentence, then list the work areas and items you intend to retain. Compare the same version of that brief across all bidders. Put “not confirmed” in an unanswered cell rather than assuming a blank means included.

  • Project outcome and areas included.
  • Proposal reference, date and contractor legal name.
  • Work and exact products included; optional items shown separately.
  • Preparation, removal, site protection and cleanup.
  • Permits or inspections: responsible party, where applicable.
  • Target schedule, payment stages and warranty documents.

Give allowances and uncertain work their own rows

An allowance is a budget placeholder for a selection or scope that is not fully settled. Ask what it covers. A unit rate for work discovered later answers a different question. Keep those two mechanisms separate from the firm price. For each open item, record who must answer it and whether the answer changes price, scope or timing.

  • Allowance: covered item, amount, included labor and selection deadline.
  • Unknown condition: what finding triggers additional work.
  • Pricing: unit, rate or method and what that price includes.
  • Authorization: who approves the change and when.
  • Evidence: record the contractor supplies to explain the added work.

Normalize one real difference at a time

Illustrative calculation: Offer A is $12,000 and excludes removal. Offer B is $13,200 and includes it. If A supplies a written $1,500 removal price, A’s comparable total becomes $13,500, assuming the other scope matches. Without that written clarification, mark A’s total incomplete; do not invent a removal allowance. This exercise compares confirmed commercial scope, not technical suitability.

Send a clarification request

Use a short message: “Please confirm the attached comparison reflects proposal [reference/date]. The following items remain open: [items]. For each, state whether it is included, excluded or provisional, and identify any price or schedule change. Please return a revised proposal where necessary.” Ask each bidder to correct your summary. Their written response is more dependable than a spreadsheet you filled with assumptions.

Record the decision and preserve the accepted version

Finish with three lines: the scope selected, the remaining uncertainty and the reason for choosing this contractor. Name the person responsible for each unresolved task. Check that the signed agreement reflects the accepted proposal and attachments. Confirm local licensing and contract requirements with the appropriate authority. Keep the comparison, revised offers and final agreement together so a later change can be compared with the actual decision.